solarpanelsforofficebuildings

Project management

Office building solar — the 12-month timeline from feasibility to commissioning

A realistic 12-month timeline for a typical UK office solar project, with dependencies and the steps that drive schedule.

Office building solar — the 12-month timeline from feasibility to commissioning

The realistic 12-month picture

A typical 200-500 kWp UK office solar project takes 9-12 months from initial enquiry to commissioning. The steps and dependencies are well-established; understanding them helps project sponsors plan capex cycles and tenant communications.

Month-by-month breakdown

Month 1: Feasibility and proposal

  • Half-hourly meter data request to DNO/supplier (typically 5-10 working days)
  • Site visit and structural / roof assessment
  • PVSyst yield modelling
  • Planning route assessment
  • Fixed-price proposal with all four funding routes

Customer decisions: funding route selection, scope decisions (battery yes/no, EV charging yes/no).

Month 2: Contract and design

  • Detailed design phase
  • Structural engineering sign-off
  • Electrical design (string layout, inverter selection, cabling routes, switchroom modifications)
  • Project programme finalisation

Customer decisions: install timing preferences (out-of-hours, weekend, summer-only), tenant communication strategy.

Month 3-4: Planning and DNO application

  • Planning route execution: Permitted Development (no application), Prior Approval (56 days), full planning (8-13 weeks), Listed Building Consent (8-13 weeks)
  • G99 grid connection application (typically 8-16 weeks DNO response time)
  • Pre-application consultations with conservation officers (heritage settings)

Customer involvement: Minimal — we manage applications.

Month 5-6: Approvals and procurement

  • Planning / Prior Approval determination
  • DNO G99 acceptance
  • Equipment procurement (panels, inverters, mounting, switchgear) — typical 8-12 week lead time on Tier-1 manufacturer products
  • Site mobilisation planning

Customer involvement: Tenant communication if relevant.

Month 7-9: Installation

  • Site mobilisation (typically 1 week)
  • Mounting system installation (2-3 weeks for 300 kWp typical)
  • Panel installation (1-2 weeks)
  • Electrical installation (2-3 weeks)
  • Commissioning testing (1 week)

Customer involvement: Site access coordination, parking management.

Month 10: Commissioning and grid connection

  • Final inverter commissioning to IEC 62446
  • DNO witnessing visit and connection approval
  • Generation start
  • Performance monitoring setup
  • Customer training session

Customer involvement: Half-day commissioning attendance recommended.

Month 11-12: Handover and documentation

  • 30-day post-commissioning performance review
  • Documentation handover (electrical certs, structural certs, warranty certs, monitoring access)
  • Scope 2 Disclosure Pack delivered
  • SEG tariff registration
  • O&M contract activation

Customer involvement: Document storage and tenant onward communication.

What drives schedule

Three factors materially affect timeline:

1. Planning route. Permitted Development can shave 3 months; full planning permission in heritage settings can add 3-6 months versus baseline.

2. DNO grid connection. In constrained networks (London UKPN areas, Greater Manchester ENWL, Bristol WPD), G99 acceptance can take 12-18 months. Always file G99 early — it runs in parallel with planning, so doesn’t directly add to programme.

3. Customer decision speed. From proposal to contract signing, customers typically take 4-12 weeks. Faster customers (sub-4 weeks) compress overall timeline; slower customers (12+ weeks) extend it linearly.

When the timeline compresses

The fastest UK office solar project we’ve delivered ran feasibility to commissioning in 5.5 months. The conditions:

  • Permitted Development (no application needed)
  • DNO connection in non-constrained area (G99 acceptance in 6 weeks)
  • Standard equipment availability (no Tier-1 product shortages)
  • Customer ready capex available (no financing approval cycle)
  • Strong project management on the customer side

Five months is achievable but exceptional. Most projects benefit from a 9-12 month planning horizon.

What happens when timelines slip

The biggest schedule risk is DNO grid connection in constrained networks. Where the local DNO indicates G99 acceptance will take 12-18 months, options include:

  • Stage 1 install at reduced output limit: Install full system but commission at reduced export, increase output when DNO grid availability allows.
  • Behind-the-meter only: Install with zero-export protection devices, avoiding G99 process entirely.
  • Wait for DNO upgrade: Some areas have committed DNO investment programmes that will resolve constraints within 18-24 months.

We work with the DNO from early proposal stage to understand the constraint position and recommend the right strategy.

Request a feasibility study including realistic programme assessment.


Accredited and certified for UK commercial work

  • MCS Certified
  • NICEIC Approved
  • RECC Member
  • TrustMark Licensed
  • IWA Insurance-Backed
  • ISO 9001 / 14001

Commercial Solar Across the UK

Our portfolio hub for commercial solar panel installation.

Smaller-scale commercial work — see solar panels for SMEs and businesses.

For Greater London-focused projects, visit London commercial solar specialists.

Specialist resource on commercial solar grants and funding.

Detailed PPA guidance at solar PPA mechanics for UK businesses.

Industrial-adjacent sector at warehouse solar installations.

For factory and industrial estate work, see manufacturing and factory solar.

Hospitality and leisure solar at solar panels for the UK hotel sector.

Heritage and faculty work at church and faculty solar specialists.