Project management
Office building solar — the 12-month timeline from feasibility to commissioning
A realistic 12-month timeline for a typical UK office solar project, with dependencies and the steps that drive schedule.
Office building solar — the 12-month timeline from feasibility to commissioning
The realistic 12-month picture
A typical 200-500 kWp UK office solar project takes 9-12 months from initial enquiry to commissioning. The steps and dependencies are well-established; understanding them helps project sponsors plan capex cycles and tenant communications.
Month-by-month breakdown
Month 1: Feasibility and proposal
- Half-hourly meter data request to DNO/supplier (typically 5-10 working days)
- Site visit and structural / roof assessment
- PVSyst yield modelling
- Planning route assessment
- Fixed-price proposal with all four funding routes
Customer decisions: funding route selection, scope decisions (battery yes/no, EV charging yes/no).
Month 2: Contract and design
- Detailed design phase
- Structural engineering sign-off
- Electrical design (string layout, inverter selection, cabling routes, switchroom modifications)
- Project programme finalisation
Customer decisions: install timing preferences (out-of-hours, weekend, summer-only), tenant communication strategy.
Month 3-4: Planning and DNO application
- Planning route execution: Permitted Development (no application), Prior Approval (56 days), full planning (8-13 weeks), Listed Building Consent (8-13 weeks)
- G99 grid connection application (typically 8-16 weeks DNO response time)
- Pre-application consultations with conservation officers (heritage settings)
Customer involvement: Minimal — we manage applications.
Month 5-6: Approvals and procurement
- Planning / Prior Approval determination
- DNO G99 acceptance
- Equipment procurement (panels, inverters, mounting, switchgear) — typical 8-12 week lead time on Tier-1 manufacturer products
- Site mobilisation planning
Customer involvement: Tenant communication if relevant.
Month 7-9: Installation
- Site mobilisation (typically 1 week)
- Mounting system installation (2-3 weeks for 300 kWp typical)
- Panel installation (1-2 weeks)
- Electrical installation (2-3 weeks)
- Commissioning testing (1 week)
Customer involvement: Site access coordination, parking management.
Month 10: Commissioning and grid connection
- Final inverter commissioning to IEC 62446
- DNO witnessing visit and connection approval
- Generation start
- Performance monitoring setup
- Customer training session
Customer involvement: Half-day commissioning attendance recommended.
Month 11-12: Handover and documentation
- 30-day post-commissioning performance review
- Documentation handover (electrical certs, structural certs, warranty certs, monitoring access)
- Scope 2 Disclosure Pack delivered
- SEG tariff registration
- O&M contract activation
Customer involvement: Document storage and tenant onward communication.
What drives schedule
Three factors materially affect timeline:
1. Planning route. Permitted Development can shave 3 months; full planning permission in heritage settings can add 3-6 months versus baseline.
2. DNO grid connection. In constrained networks (London UKPN areas, Greater Manchester ENWL, Bristol WPD), G99 acceptance can take 12-18 months. Always file G99 early — it runs in parallel with planning, so doesn’t directly add to programme.
3. Customer decision speed. From proposal to contract signing, customers typically take 4-12 weeks. Faster customers (sub-4 weeks) compress overall timeline; slower customers (12+ weeks) extend it linearly.
When the timeline compresses
The fastest UK office solar project we’ve delivered ran feasibility to commissioning in 5.5 months. The conditions:
- Permitted Development (no application needed)
- DNO connection in non-constrained area (G99 acceptance in 6 weeks)
- Standard equipment availability (no Tier-1 product shortages)
- Customer ready capex available (no financing approval cycle)
- Strong project management on the customer side
Five months is achievable but exceptional. Most projects benefit from a 9-12 month planning horizon.
What happens when timelines slip
The biggest schedule risk is DNO grid connection in constrained networks. Where the local DNO indicates G99 acceptance will take 12-18 months, options include:
- Stage 1 install at reduced output limit: Install full system but commission at reduced export, increase output when DNO grid availability allows.
- Behind-the-meter only: Install with zero-export protection devices, avoiding G99 process entirely.
- Wait for DNO upgrade: Some areas have committed DNO investment programmes that will resolve constraints within 18-24 months.
We work with the DNO from early proposal stage to understand the constraint position and recommend the right strategy.
Request a feasibility study including realistic programme assessment.