If you are comparing installers for an office roof, this page sets out what each of them should do and in what order, so you can check a proposal against it. For the price side, see what office solar costs; to ask about a specific building, send an enquiry. We reply by email.
- 01
Desk feasibility
Before any visitYou send half-hourly meter data and a roof plan. The installer models the yield for your roof, sets out sizing options against your daytime demand, checks the planning route and returns a modelled proposal.
What you receive
- Yield model for your roof
- Sizing options against your demand
- Cost range for each option
- Planning route assessment
- Tax relief and export tariff check (AIA, SEG)
- 02
On-site survey
Before a fixed priceStructural and electrical engineers visit. The roof is assessed to BS EN 1991 for the added dead and wind loads, the main switchroom is checked, cable routes are designed, shading is verified on site and the incoming supply capacity is confirmed.
What you receive
- Structural calculation
- Electrical single-line diagram
- Cable route plan
- Final inverter specification
- Fixed-price proposal
- 03
Planning and the grid application
Runs alongside designThe planning route (permitted development, prior approval, or a planning application where one is needed) and the G99 grid connection application to the local network operator are dealt with at this stage. These two consents, not the roof work, usually decide when the system can be switched on.
What you receive
- Planning notification or application
- G99 application to the network operator
- Listed building consent where the building is listed
- Building Regulations sign-off route
- CDM 2015 pre-construction information
- 04
Installation on the roof
On siteMounting frames, panels, inverters and cabling go in, and the system is tied into the main switchgear. Time on the roof depends on the size of the array and on access, so ask each installer for a dated programme. An MCS-certified installer, electrical certification and CDM 2015 safety management are what to require.
What you receive
- Mounting frames and panels fitted
- Inverters installed
- Switchgear connection made
- Network operator witness testing where it asks for it
- Electrical installation certificate
- 05
Commissioning and handover
At switch-onThe system is commissioned to IEC 62446 and handed over with an operation and maintenance manual, electrical and structural certificates, monitoring access and the warranty documents for the panels, the inverters and the workmanship. Warranty terms differ by manufacturer and installer, so read each one. Ask for the generation data in a form your Scope 2 reporting can use.
What you receive
- Operation and maintenance manual
- Electrical and structural certificates
- Warranty documents
- Monitoring login
- Smart Export Guarantee application details
- 06
Operation and maintenance
After handoverAsk whether the first years of maintenance are included in the price. A typical contract sets scheduled inspections, a contracted response time for faults, periodic electrical inspection and testing, and an annual performance report against the design model. Check each term before you sign.
What you receive
- Scheduled inspections
- Cleaning where needed
- Reactive fault response
- Annual performance review
- Periodic electrical inspection and test
What installation involves on an occupied office
Most of the work happens where staff never go. Four parts of it do touch the running of the building, and a good programme shows each one with a date.
- Lifting. Panels, frames and ballast reach the roof by crane or hoist. That needs a set-down area and, for a short time, part of a car park or service yard.
- Fixing. On a flat office roof the usual method is a ballasted frame that avoids penetrating the waterproof membrane. The structural engineer's statement to BS EN 1991 confirms the roof can carry it. Where it cannot, see lightweight solar for commercial buildings.
- Connection. Tying the system into the main switchgear needs a planned electrical shutdown. Ask whether it can be done outside working hours.
- Safety management. Installation is construction work. Under regulation 5 of the Construction (Design and Management) Regulations 2015, a client must appoint a principal designer and a principal contractor in writing where more than one contractor will work on the project. On an office roof that is normal, so ask who will hold each role.
The consents that set the timetable
| Consent | When it applies | What it means for the programme |
|---|---|---|
| Permitted development (England) | Rooftop array up to 50 kW on a non-listed, non-domestic building, within the Class J height and roof-edge limits | No application. Keep a record of how the limits are met. |
| Prior approval (England) | Rooftop array above 50 kW | The council decides on design and external appearance, including glare. The period is 56 days. |
| Planning permission, and listed building consent where the works affect a listed structure | A listed building or a building in its curtilage | Permitted development does not apply. Allow for a full application. |
| G98 notification | Systems up to 16A per phase (about 3.68 kW single-phase, about 11 kW three-phase) | Connect, then notify the network operator within 28 days. Few office arrays are this small. |
| G99 application | Everything larger, so almost every office system | The network operator must approve it before the system connects. Apply as soon as the design is fixed. |
| Landlord's consent | A leased building | Needed before any order is placed. See landlords and tenants. |
Scotland, Wales and Northern Ireland have their own permitted development rules. The full position, nation by nation, is on the page about planning permission for solar panels on commercial buildings.
Who carries out the installation
The installer you appoint does, with a structural engineer and, on larger systems, a specialist for the high-voltage or switchgear work. This site is a guide and installs nothing. Before you appoint, ask each installer for five things:
- its MCS certificate number for solar PV, and what else it holds (the accreditations page explains what each scheme covers);
- confirmation that the inverters it proposes are on the Energy Networks Association type-test register, which the G98 and G99 rules require;
- who submits the G99 application and who deals with the network operator's reply;
- who holds the principal designer and principal contractor roles under CDM 2015;
- a fixed, itemised price and a dated programme.
What installation costs
The one official benchmark is the DESNZ 2025/26 average installed cost for non-domestic systems of 10-50 kW: £1,259 per kW. DESNZ publishes no series above 50 kW, and larger systems usually cost less per kW, so treat it as an upper reference for a big office roof and compare every quote with it. The cost guide sets out what moves the price, and the Annual Investment Allowance page covers the tax relief a company can claim. Estates with several buildings should read solar panels for business parks, and public bodies solar panels for the public sector, because the buying route differs for both.
Office solar installation: questions buyers ask
How long does solar panel installation take on an office building?
There is no standard figure, and we do not quote one. Two periods are fixed in law or in the connection rules: in England an array above 50 kW needs the council's prior-approval decision, which has a 56-day period, and a system small enough for G98 is notified to the network operator within 28 days of commissioning. Almost every office system is larger than that and needs a G99 application approved before it connects, and network operators do not publish one timescale for it. Ask the operator for its current G99 timescale and ask each installer for a dated programme.
Do we need planning permission to install solar panels on an office?
Usually not in England. Rooftop solar on a non-domestic building is permitted development under Class J of Part 14 of the General Permitted Development Order up to 50 kW, provided it stays within the height and roof-edge limits. Above 50 kW it needs the council's prior-approval decision on design and appearance. A listed building, or a building in the curtilage of one, is outside Class J, so it needs planning permission, and listed building consent where the works affect a listed structure. Scotland, Wales and Northern Ireland have their own rules.
Can the office stay open while the panels are installed?
The work is on the roof and in the plant and switch rooms, so occupied floors are not normally the work area. The steps to plan for are the lifting of materials to the roof and the electrical shutdown needed to connect the system to the main switchgear. Ask each installer to show both in its programme, with dates and times, and to say whether the shutdown can be done outside working hours.
Who applies to the network operator for the grid connection?
The installer normally submits the G99 application, because it needs the inverter and protection details from the design. Confirm that in writing before you appoint, and ask what happens to the price and the system size if the operator offers less export capacity than was applied for.
What should an office solar installation quote include?
A fixed price with the panels, inverters, mounting system, scaffolding or edge protection, lifting, cabling, switchgear work, the G99 application, commissioning and handover documents each itemised; the modelled yearly generation and the share your building will use; the warranty terms; and what is excluded. Compare the price per kW with the DESNZ 2025/26 average of £1,259 per kW for non-domestic systems of 10-50 kW, bearing in mind that larger systems usually cost less per kW.